- FG equipment is brought to the platform via a small barge and is hoisted onto the platform using the existing platform's crane (if any). If not available, FG can bring their own equipment up to the platform via a portable manual winch.
- Assuming that the tip needs repair and this can be done on the platform itself, than it is advised to bring the tip to the platform.
- The FG Arch Frame is erected over the flare tip.
- Two guide wires are pulled to the main-platform.
- The flare tip is lifted up and hooked onto the 2 guide wires.
- The flare tip is brought to the platform via these two guide wires.
- Repair is carried out on the platform.
Installation of the repaired flare tip is the reversed procedure.